Due dates in templates
The four ways a template task can get its due date, and which one you actually want.
On this page
This is the setting that decides whether a template is useful or annoying, and it's the one most often set wrong.
Each task in a template gets its due date from one of four rules, chosen under Due date in the task's setup: Fixed date, After period end, Apply date or After predecessor. Choose No due date for a task that shouldn't have one.
Fixed date
A month and day, the same every year.
When the template is applied, the date lands in the current year, or next year if that day has already passed this year. So Mar 15 applied on Feb 2, 2026 is due Mar 15, 2026, and applied on Apr 20, 2026 is due Mar 15, 2027.
Right for a genuine deadline that never moves. Most things that feel fixed are actually tied to a period, and After period end handles a fiscal-year client without a second copy.
After period end
N days after the period ends.
This is the right answer for most recurring work. A bookkeeping task due 10 days after the period ends is due Jan 10 for December's books and Feb 10 for January's, without anyone editing anything.
"The period" is the one entered when the template is applied, or the one a recurring schedule creates. It follows each client's own fiscal year end, so one template covers a December client and a June client.
Because it's anchored to the period rather than to when you started, work applied late still carries its real deadline. Applying December's work in February doesn't quietly move December's deadline.
Apply date
N days after the apply date.
Anchored to the day the template was applied, not to any period. Right for onboarding and for anything where the clock starts when the work starts.
Send engagement letter, 2 days after the apply date behaves correctly whenever you onboard, which is the point.
Apply date is the wrong choice for periodic work, and it's the most common mistake. A quarterly task set to Apply date is due relative to whenever somebody got around to creating it, so a late start silently produces a late deadline and nothing flags it.
After predecessor
N days after the tasks it depends on reach the point you set.
Available only in a template with more than one task, because it's measured from another task in the same job. It's what makes a realistic chain: review due 3 days after prep, delivery due 2 days after review.
The task has no due date while it waits. When the tasks it depends on reach the role set under Depends on, it unblocks and gets its date: that day plus the days you set.
Its strength is also its risk: if the earlier task slips, everything behind it slips, and no absolute deadline pulls it back. Use it for internal handoffs, and an absolute rule for anything with a real deadline at the end.
Choosing
- A deadline that never moves → Fixed date
- Recurring work tied to a period → After period end
- Onboarding or one-off work → Apply date
- An internal handoff inside a job → After predecessor
A well-built tax template usually mixes them: the filing task is due after period end, and the internal prep and review steps run after their predecessors.
A test worth running
Apply the template to a test client twice, once with this period and once with a period two months in the past.
If the second one produces dates two months earlier, your rules are right. If both land on the same days, you've used Apply date where you meant After period end.
Notes and limits
- After period end needs a period end date. A bulk apply to many clients sends none, so those tasks arrive without a due date; apply to one client at a time, or use a recurring schedule.
- Changing a rule doesn't change dates on work already created.
- Template due dates are not moved off weekends or holidays.