Sign-offs and locking
Sign off a workpaper level by level, what happens when its document changes, how reopening works, and what finalizing the binder locks.
On this page
A sign-off records that a named person reviewed a specific version of a workpaper's document. The version is what makes it mean something: if the document changes afterwards, the sign-off no longer counts.
Sign-off levels, reopening and finalizing
Sign off
LedgerOS sets up two sign-off levels for your firm: Prepared, then Reviewed, the final level. The bar shows a button for each level that isn't signed: Sign as Prepared, Sign as Reviewed. Once signed, the level shows who signed and the date.
Levels are signed in order. A workpaper must have a document linked before anyone can sign it, and none of its review notes can be open. Each sign-off records who signed, when, and which version of the document they signed.
When the document changes
If a new version of the document is uploaded after a level was signed, that level no longer counts. The bar shows cleared · re-uploaded beside it, with the version it was signed on, for example cleared · re-uploaded (signed on Version 2), and in the binder the workpaper's status reads Re-review · doc changed. Look at the new version and sign again.
This is what keeps a sign-off from passing as current when the document under it changed. A workpaper that looks signed at a glance but reads Re-review · doc changed is the one to work first.
Reopen
- The reopen button beside a signed level (Reopen Prepared sign-off, for example) clears that level and every level after it. Reopening Prepared also clears Reviewed, because the review was of work that is about to change.
- Reopen all clears every level on the workpaper.
Reopening is recorded with the workpaper's document, including which later levels it cleared.
Finalize the binder
When the work is done, click Finalize binder in the binder's header. Finalizing locks every workpaper in the binder: the bar shows Locked. Signing alone never locks a workpaper.
Finalize binder is available only when the binder is ready: no open review notes, and every workpaper signed at the final level on its current document. Until then, hovering over it says what is missing, for example Not ready to finalize — 2 open review notes, 1 unsigned workpaper.
On a locked workpaper, only owners and admins can sign, reopen a level, or click Unlock. A finalized binder says Binder finalized with the date. To reopen it, an owner clicks Reopen beside it (or Reopen binder in a workpaper's … menu), which unlocks every workpaper. Anyone else sees An owner can reopen it to make changes.
Why can't I…
…sign this level? LedgerOS says why:
- Sign off as Prepared first — an earlier level isn't signed.
- This workpaper has 1 open review note. Clear it before signing off. — clear or close the note first. See Review notes.
- Link a document before signing off — the workpaper has no document yet.
- This workpaper is locked. Ask an owner or admin to unlock it before signing. — the binder was finalized.
…unlock or reopen this workpaper? It is locked, and only owners and admins can: This workpaper is locked. Only an owner or admin can unlock it.
…finalize the binder? It isn't ready (see above), or your role can't manage tasks: You do not have permission to finalize a binder.
…reopen the binder? Only an owner can: Only an owner can reopen a finalized binder.